Activities concerning groundwaters and/or the protective zones of abstraction areas according to annex 1 of the government order no. 20/2001 (11. 14.) Korm. on the environmental impact assessment (extract)
Activities and/or facilities necessary for their realisation that can be granted an environmental permit only after having performed a detailed environmental impact assessment
Activities and/or facilities necessary for their realisation and major modifications where the necessity of performing a detailed environmental impact assessment depends on the decision of the inspectorate
|
2. |
Shift to intensive agricultural land use/farming on areas classified as "cultivation ceased" from 50 ha, or |
- in the protective zone of a groundwater abstraction site
, in a protected nature
- reserve or in its protective zone from 1 ha
|
|
3. |
Improvement of flat land from 500 ha or of hilly land from 300 ha, or in case the area to be improved covers a protected nature reserve or its protective zone, or the protective zone of a groundwater abstraction site on at least 5 ha |
|
6. |
Livestock installations from 100 standard animals/ha (projects not included in Chapter "A"); in the protective zone of a groundwater abstraction site, in a protected nature reserve or in its protective zone, on a nature area, on a sensitive nature area in case of poultry from 5 standard animals, in other cases from 24 standard animals |
|
14. |
Petroleum and natural gas extraction (projects not included in Chapter "A"); test drillings only in a protected nature reserve or in the hydrogeological protective zone of a groundwater abstraction site |
|
72. |
Hydroelectric power stations from 20 MW electric output; in the protective zone of a groundwater abstraction site and in a protected nature reserve with no size limitation |
|
73. |
Geothermal power stations from 20 MW electric output; in the protective zone of a mineral water, medicinal water and drinking water abstraction site and in a protected nature reserve with no size limitation |
|
80. |
Groundwater use (projects not included in Chapter "A") if the daily abstraction from one object or object group exceeds |
|
1 000 m 3 |
from |
shallow ground water |
|
1 000 m 3 |
from |
karstic thermal water |
|
5 000 m 3 |
from |
deep groundwater and karstic water |
|
10 000 m 3 |
from |
bank filtration water |
|
2 000 m 3 |
from |
confined thermal water |
|
100 m 3 and 33% of the current yield of the spring |
|
95. |
Storage of natural gas from 20 000 m 3 total storage capacity (projects not included in Chapter"A"); underground storage of other combustible gases from 10 000 m 3 ; in a protected nature reserve in both cases from 5 000 m 3 |
|
108. |
Establishing of a new permanent flood-control work in the protective zone of a groundwater abstraction site or in a protected nature reserve |
|
109. |
Waste water treatment plants with a capacity from 20 000 population equivalent (projects not included in Chapter "A"); in the protective zone of a groundwater abstraction site, in a protected nature reserve or in its protective zone with no size limitation |
|
111. |
Independent sewage sludge deposition sites from 100 tlyear dry matter; in a protected nature reserve or in its protective zone, or in the hydrogeological protective zone of a groundwater abstraction site with no size limitation |
|
112. |
Sites depositing sewage by irrigation from 50 ha; in a protected nature reserve or in its protective zone, on a nature area, or in the "B" hydrogeological protective zone of a groundwater abstraction site with no size limitation |
|
113. |
Filtration-field drying systems from 15 ha; in a protected nature reserve or in its protective zone, on a nature area, or in the hydrogeological protective zone of a groundwater abstraction site with no size limitation |
|
126. |
Deep drillings with an established drilling facility from 650 m drilling depth (unless being part of another activity under Chapters "A" and "B") in the protective zone of a groundwater abstraction site or in a protected nature reserve |
|
131. |
Dams and other installations designed for the holding back or permanent storage of water, where the amount of water held back or stored is at least 2 million m 3 (projects not included in Chapter "A"); in the protective zone of a groundwater abstraction, in a protected nature reserve or on a nature area with no size limitation |
|
132. |
Artificial groundwater recharge schemes (not included in Chapter "A") |
|
133. |
Local water regulation on a land not planned to be developed |
- from 500 ha plain land,
- from 300 ha hilly land,
- in the protective zone of a groundwater abstraction, in a protected nature reserve, on a nature area, on a sensitive nature area, in an ecological (green) corridor outside inhabited areas with no size limitation
|
|
134. |
Fish pond or a system of fish ponds from 30 ha; in the protective zone of a groundwater abstraction, in a protected nature reserve or in its protective zone, on a nature area or on a sensitive nature area with no size limitation |
|
135. |
Standing water and backwater (oxbow) regulation from 5 ha surface size to be regulated or from 1 km shore length; in the protective zone of a groundwater abstraction, in a protected nature reserve, on a nature area, on a sensitive nature area or in an ecological (green) corridor with no size limitation |
|
136. |
River regulation or canalisation from 3 km river length; in case of curve cutting or in the protective zone of a groundwater abstraction, in a protected nature reserve, on a nature area, on a sensitive nature area or in an ecological (green) corridor with no length limitation |
|
137. |
Water course regulation (except for removal of silt and management of the bank for maintenance and for restoring the original draining capacity) from 1 km current length; in the protective zone of a groundwater abstraction, on a nature area, on a sensitive nature area, in an ecological (green) corridor from 200 m current length, in a protected nature reserve with no size limitation |